Practical Experience
Leads To Real World Results.
Case Study 1: Boynton Yards
J.C. Higgins / Plumbing & Mechanical / Somerville, MA
The design team for this 9-story, 290,000 sq. ft lab/office building wanted to preserve as much open space as possible while accommodating the needs of future tenants. We walked them through solutions and worked with the engineering team to achieve both goals.
Case Study 2: ASML Boiler Plant Upgrades
Corporate Construction / General Contractor / Wilton, CT
When the client needed to replace two existing boilers with five new ones without shutting the heating system down, we used a 3D scan of the building to meticulously plan how to work around the current piping and mechanicals while keeping the plant continuously running.
Case Study 3: Yale University Chiller Addition
Tucker Mechanical / Mechanical Contractor / New Haven, CT
To add a new 2,500 ton centrifugal chiller and other upgrades to a plant, several existing services needed to be re-routed as efficiently as possible during a brief shutdown. We worked with the other trades to make sure everything fit perfectly and quickly into place.